多时段露天矿生产计划整体优化模型

孙效玉1, 邓鹏宏2, 赵明3   

  1. (1. 东北大学 资源与土木工程学院, 辽宁 沈阳110819; 2. 鞍钢矿业公司 决策支持部, 辽宁 鞍山114004; 3. 中煤科工集团沈阳设计研究院有限公司 露天工程事业部, 辽宁 沈阳110015)
  • 收稿日期:2015-11-16 修回日期:2015-11-16 出版日期:2016-10-15 发布日期:2016-10-14
  • 通讯作者: 孙效玉
  • 作者简介:孙效玉(1963-),男,内蒙古赤峰人,东北大学教授.
  • 基金资助:
    “十二五”国家科技支撑计划项目(2015BAB15B01); 国家自然科学基金创新研究群体项目(71321001/01).

Integrated Optimization Model of Multi-period Open-Pit Mine Production Scheduling

SUN Xiao-yu1, DENG Peng-hong2, ZHAO Ming3   

  1. 1. School of Resources & Civil Engineering, Northeastern University, Shenyang 110819, China; 2. Resources Planning Management Department, Ansteel Mining Company, Anshan 114004, China; 3. Open-Pit Mine Engineering Business Unit, CCTEG Shenyang Engineering Company, Shenyang 110015, China.
  • Received:2015-11-16 Revised:2015-11-16 Online:2016-10-15 Published:2016-10-14
  • Contact: SUN Xiao-yu
  • About author:-
  • Supported by:
    -

摘要: 针对数学优化方法在露天矿进度计划应用中存在的只对单一时段计划进行优化,或是对多时段计划进行分段优化,没有实现全时段整体优化的问题,在前后时段0-1整数规划和大小时段0-1整数规划两种模型分段优化的前期工作基础上,提出了露天矿整体优化的0-1整数规划模型,并针对计算速度慢的问题,提出了相应的改进措施.该模型既实现了多时段生产计划的整体优化,又解决了分段优化无解的隐患,还保证了速度和精度,不仅可实现用下层计划验证上层计划,而且可用于由下层计划导出上层计划,其实用性和通用性更好.

关键词: 露天矿, 生产进度计划, 0-1整数规划, 线性规划, 整体优化, 多时段

Abstract: To solve the integrative optimization of multi-period plans in the applications of open pit production only focused on single-period or multi-period optimization with mathematical optimization methods, a 0-1 integer programming model for the integrated optimization was proposed on the basis of previous works of 0-1 integer programming models for “before and after” periods and for “large and small” periods. The corresponding improvement measures were put forward for low computing speed. The model realizes the integrative optimization of multi-period plan, avoids the potential danger of no solution to the discrete optimization, and also guarantees the computational speed and accuracy. The model can be used to verify upper plan with lower plan and to derive upper plan from lower plan, and shows a better adaptability and versatility.

Key words: open-pit mine, production scheduling, 0-1 integer programming, linear programming, integrative optimization, multi-period